The project involves several pollution control and environmental conservation measures and the 14 sub projects brought under five main categories are given below:
Desilting and Dredging Works.
- Desilting and Dredging of the Lakes.
- Deepening & Widening of spill channel.
- Restoration of Island.
Catchment Area Treatment:
- Afforestation, Creation of Buffer Zones.
- Construction of check dams, silt traps, toe walls & cascading for controlling silt entry.
Sewerage Pollution Prevention Schemes & Construction of Garland Drains around the Lower lake.
Shoreline and Fringe Areas Management.
Water Quality Monitoring
- Deweeding
- Water Quality Monitoring laboratory.
- Installation of floating fountains.
- Aquaculture.
|